Larkana radio transmitter inoperative for seven years
LARKANA: The 100 kiloWatt medium wave transmitter of the Radio Pakistan Larkana which was planned to be made functional in 2008 is yet to be put in operation due to technical reasons.
It was installed near Chuharpur village located along the Larkana-Naudero Road after complaints by listeners about low signals. Although the work for the installation had almost been completed, some technical issues hindered commissioning of the transmitter, Pakistan Broadcasting Corporation’s
Larkana station director Mukhtiar Malik, who visited the site a couple of weeks ago, told Dawn.
The Larkana station was commissioned in October 1995 and the then Pakistan Peoples Party chairperson Benazir Bhutto had inaugurated it. Since then it had been experiencing turbulence because of its weak transmitter, he said.
During the regime of General Pervez Musharraf, the PBC sanctioned the 100kW transmitter for Larkana but it was shifted to Turbat before it could be installed at the project site.
The two-kW transmitter meant for airing FM-93 broadcast within a radius of 80 kilometres is also an enigma for listeners, who complain of trouble in receiving the broadcast. It appeared that the FM-93 transmissions can hardly be heard within a radius of 20-25 kilometres.
“I had time and again taken up the matter with the PBC headquarters but without any response,” said Mr Malik.
In a letter addressed to the PBC controller on June 24, 2014 it was mentioned that two out of the four panels of the transmitter installed on June 23, 2010 were not working properly.
Sources in the PBC said that the listening range of the transmitter had now reduced to just a quarter of its projected capacity. Also, the transmission was not so clear, they said, adding that the situation had been persisting for four years.A team of technical experts led by Mr Shakeeluddin visited the transmitter site to rectify faults, Mr Malik said, and expressed the hope that the medium wave transmissions from the Larkana stations would start within a couple of months.
However, Mr Shakeeluddin, when contacted for his comment, declined to say anything about the status of the troubleshooting work. He said the planning and development wing of PBC headquarters could be asked about any progress in this regard.
In 2008, three high-power transmitters were imported for installation at Multan, Larkana and Hyderabad but only one of them could be installed and made operational on Aug 17, 2014 at Hyderabad, sources said. The fate of the other two transmitters still hanged in the balance, they said.
Most people at the helm of affairs here in Larkana remain indifferent over such issues, according to Mr Malik. He referred to a trouble that hit the Khairpur station in the past, and said that Chief Minister Syed Qaim Ali Shah had immediately sanctioned Rs90 million to overcome the problem.
Sources at the Larkana station told Dawn that even a standby generator to ensure an uninterrupted power supply was yet to be made available here.
The railway authorities were playing delaying tactics for necessary permission with regard to a high tension electricity cables required to be erected across the railway line to reach the transmitter site, the sources said, adding that the PBC had already made the payment as demanded by the railway authorities.
You may also like
Archives
- March 2024
- February 2024
- January 2024
- September 2023
- July 2023
- March 2023
- February 2023
- January 2023
- April 2022
- March 2022
- February 2022
- September 2021
- August 2021
- July 2021
- April 2021
- February 2021
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- December 2019
- October 2019
- September 2019
- August 2019
- July 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- June 2018
- December 2017
- November 2017
- October 2017
- September 2017
- March 2017
- February 2017
- November 2016
- October 2016
- September 2016
- July 2016
- June 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- November 2015
- October 2015
- September 2015
- August 2015
- June 2015
- May 2015
- March 2015
- February 2015
- January 2015
- November 2014
- August 2014
- July 2014
- June 2014
- May 2014
- April 2014
- March 2014
- February 2014
- January 2014
- December 2013
- November 2013
- October 2013
- September 2013
- August 2013
- July 2013
- June 2013
- May 2013
- April 2013
- March 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
- September 2012
- August 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
- December 2011
- October 2011
- August 2011
- July 2011
- June 2011
- May 2011
- April 2011
- March 2011
- February 2011
- January 2011
- December 2010
- November 2010
- October 2010
- September 2010
- August 2010
- July 2010
- June 2010
- May 2010
- April 2010
- March 2010
- February 2010
- January 2010
- December 2009
Calendar
M | T | W | T | F | S | S |
---|---|---|---|---|---|---|
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Leave a Reply